ReDew Anson

Jones County, Texas · ERCOT West

600
MW Cleared Interconnection

A data center and battery storage campus on a cleared 600 MW interconnection at Phantom Hill 345 kV — energized in 25–50 MW tranches behind an anchor tenant. First block 50 MW, 2028.

ReDew Anson project site aerial view

Campus footprint in the NW corner of the parcel, adjacent to Phantom Hill 345 kV · Jones County, Texas

Land Control
45 ac owned · 123 ac pending
Environmental
Complete
Interconnection
GINR In Preparation
Configuration
LDUPS · Co-located
Target NTP
Mid-2027
First Block Energized
2028

Project Specifications

Built for ERCOT. Built for tenants. Built to last.

Technical

  • Cleared IC600 MW
  • POIPhantom Hill 345 kV
  • ConfigurationLDUPS · In-Series
  • BatteryTerraFlow Vanadium Flow
  • On-Site GenerationNatural Gas
  • ISO RegionERCOT West

Location

  • CountyJones County, TX
  • Adjacent GenerationENGIE Anson Solar
  • Stargate Proximity~19 mi (Abilene)
  • Grid Strength2,633 MVA SCR

Timeline

  • Development Start2025
  • GINR SubmissionIn Preparation
  • IA & NTPMid-2027
  • First Block (50 MW)2028

Project Partners

Proven teams. Established relationships.

Technology & Turnkey

TerraFlow Energy Operating

Vanadium flow battery + integrated turnkey scope across application prep, single line, architecture, site design, and IC engineering.

Environmental

ESE Partners

Phase I ESA and Desktop CIA complete; additional scope in progress through NTP.

Fiber Connectivity

FiberLight

Tenant-grade fiber connectivity. Quote received; LOI in process.

Interested in ReDew Anson?

We're open to conversations about tenant capacity, strategic partnership, and investment.